The project flow

How a project actually runs

The method says what the phases and gates are. This page shows how a project moves through them in practice: the tom_specs process that walks it step by step, the review rounds inside the documents, the gates run against checklists, and the same process for a change to an application that is already running.

The flow is not only written down; it is an executable process definition. A process engine knows the position of every project, queues the prompt of the next step for an agent, waits for your review and takes your decision at each gate. Tom UAM, the first project, has gone through Phases 1 and 2 this way and is in Phase 3.

Eight phases, eight gates - and change mode

The creation path runs from the free-form idea to production; every arrow carries a gate. A change to a running application is not a new project: it is a run of the same process in change mode, with a Phase 0 in front and a Phase 8C at the end.

The TomSpecs project flow: phases 1 to 8 with gates G1 to G8, and change mode with Phase 0, the affected phases and Phase 8C with gates G0 and G8C, leading to production.
Every gate can fail and send the work back to its phase. A defect found later re-opens the phase it came from.
ONE DEFINITION

The tom_specs process

Phases 0 to 8 and 8C, each with its steps, sub-steps and a gate, stored in _ai/processes/tom_specs/. Every step has a role and a prompt; repeatable steps loop until their condition holds.

RUNS

One position per run

A project can have several runs side by side - the initial development and a change, say - each with its own position, parameters, sessions and queue lane.

YOUR TURN

Steps that are yours

Reviews and gate decisions are user steps. The process stops there, shows the document, and moves on when you finish the round or decide.

The Blueprint is the expansion point

Phase 2 produces one document covering the whole system; Phase 3 expands defined regions of it into twelve. The mapping is part of the object model and is checked by its validator, so Phase 3 is a bounded, checkable task rather than "write twelve documents". A projection then routes every section to the code it feeds.

The Solution Blueprint fans out through the section mapping into the twelve Phase-3 documents; the CodeSpecs Generation Projection routes every section to its code area.

Inside Phases 2 and 3: a fixed step plan

Both specification phases run the same steps. Each step plans before it acts: it prepares its files, files its own todos and queues them as one walk, and ends by showing you the result.

The step plan: initial version, deepening, a repeated iteration of question rounds, a structural and requirements pass and a consistency round, final consistency and result, each with your review, then gate G2 or G3. Every step writes its step folder.

The iteration repeats until no relevant question is left open; Tom UAM's Blueprint took three iterations (03_01_… to 03_03_…). Phase 3 runs the plan in three waves of documents in dependency order, so a document is written only after what it builds on is settled. The step folders keep the document as each step left it, together with that step's answers.md and review document, so every decision can be traced to the round that made it.

Review rounds happen inside the documents

Questions, comments and proposed changes are written into the specification itself, where the text gives them their context. You answer in the MD Browser; the agent applies, records and only then removes.

A review round: annotate, answer in the MD Browser, finish the round, apply, record, remove. A team review runs as the subprocess team_document_review: prepare copies, members review, merge, consolidate, return to the step.

The notation

A question block names its topic, offers lettered options with the recommended one in bold, states a working assumption, and leaves room for the answer. Comments carry their author and change time. Inline changes use CriticMarkup - {~~ 30 ~> 5 ~~}, {++ added ++}, {-- removed --} - and are accepted or rejected one by one. All nine language runtimes read and write the same notation.

Team rounds

A review step can start the team_document_review subprocess: each member gets a copy, the copies come back and are merged with authors, votes and individual answers, and where members changed a passage differently a conflict block shows the alternatives for a decision.

Sessions expire after 30 minutes of inactivity.
> ⬆️ **C-12** (Alexis): Too long for shared kiosk devices.
> **❓ BQ-90 — C-12 kiosk timeout:** a shorter
> timeout for kiosk devices only, or for every device?
> - **(a)** kiosk devices only, 5 minutes
> - (b) every device, 15 minutes
>
> *Recommendation:* (a).
> *Working assumption until answered:* (a).
>
> **Answer:** (a)

Quality inside a phase

A gate checks a set of deliverables that should already be individually approved. Each deliverable loops between a progress role and an independent quality role; each specification document moves from Draft to Accepted.

The per-deliverable loop between progress role, quality role and human review, and the document sequence Draft, Reviewed, Verified, Accepted with every failure returning to Draft.

Producing a derived deliverable regularly reveals a gap in its basis. Then the process goes back to the phase that owns the defect instead of working around it.

Phase re-entry: a specification gap found during CodeSpecs work goes back to Phase 3, a CodeSpecs issue found during implementation back to Phase 4.

Gates run against checklists

Every gate - G0 to G8 and G8C - has a generic checklist that a project copies and adapts. The gate step takes in what you answered since the last step, checks each criterion against evidence, writes a report with a recommendation, and shows it to you with the decision buttons.

Generic checklist, project checklist, gate prompt, gate report, your decision; passed leads through post-gate todos to the next phase, failed goes back to the gate's onFail step.

A project may add and narrow checklist items freely; removing one needs a recorded justification that the gate report shows. Thresholds - coverage, performance, acceptable defects - come from the project's own quality plan and architecture specification, not from the checklist. Reports are kept with the specification (quality/evidence/gates/), so a gate result can be replayed against the criteria in force when it was taken. The criteria of each gate are on the method page.

Phase 4: two passes with a fixed boundary

Phase 4 is neither a compiler pass nor free authoring. A gate at its start checks that the specification can carry code at all; the extract generator copies, the authoring agent judges, and each generation unit's mapper writes the code from the agent's IR.

Phase 4: the specification, Stage A starting gate, Pass 1 extract, Stage B verdicts, Stage C todo tree; Pass 2 authoring agent writes the IR, mappers per generation unit write the code, standard emitters write OpenAPI and other standards, validation runs 47 checks.
STAGE A

A starting gate

Complete against the schema, valid on the instance tier, every section routed, every required argument backed by a filled source. A specification with holes produces code with inventions; this gate stops it first.

PASS 1

Extracts that only copy

One extract per code area - 27 of them - holding every routed field verbatim with its source. The generator may copy and index; it may never summarise, rephrase or choose a name.

STAGE B

Gaps become questions

Per area: sufficient, not applicable, or insufficient - naming the section that should have carried the missing input. Each gap is a decision-needed todo that pauses the run until the specification answers it.

PASS 2

The IR, then any stack

The agent writes the IR in 31 steps, each from its own extracts. The mappers write a Dart trio by default, or TypeScript, Go, Java or C# units; 47 checks validate the result.

Phases 5 to 8

The process defines their steps: a test plan and derivation by kind (acceptance, process, boundary, authorization, data, integration) with a red baseline; implementation in build order with code and security reviews; a test deployment run against the quality plan, documentation and sign-off; production configuration, migration and rollback, hardening, the optional multi-tenant setup and the rollout. They run on general agent work and the workspace's test and git tooling; no project has reached them yet, and they have no TomSpecs-specific tools so far.

Change mode

The first step of every run asks whether it is the initial development or a change. A change gets an id that names its branch (change/<id>), its folder and its commits, and runs:

PhaseIn change mode
0The intended effect and its exclusions; an impact walk over every section, code area, test and code unit with a verdict and the effort; the principles the change touches. You accept the impact at G0.
1-3The existing documents are updated - only the impact set, wave by wave through the traceability of the model. Every review shows the last round's marks and a read-only copy against the commit the change started from.
4The CodeSpecs and IR delta, computed by section token.
5-6Against a frozen test baseline; tests the change makes false are marked expected to fail, then inverted.
8CThe full regression against the baseline, and a tested pull request. G8C checks that nothing outside the impact set changed.

Roles

Every agent step names its role, and the role's instructions travel with the prompt. A progress role and an independent quality role work each phase as separate agents - one agent checking its own work is not independent verification. The roles defined today:

RoleWorks on
spec_authorThe Project Idea, the Blueprint and the Phase-3 documents
spec_quality_managerReview and consistency of the specification, the gates of Phases 1 to 3
codespecs_designerPhase 4: the starting gate, extraction, the verdicts per area, the todo tree and the authoring
codespecs_quality_managerThe Phase-4 gates and validation
test_managerTest plan, derivation and baselines of Phase 5, acceptance runs
senior_developer, code_reviewerImplementation and its code review
security_specialistSecurity review from Phase 3 on, and the security gate items
release_engineerThe test deployment of Phase 7 and the production release of Phase 8
change_analystPhase 0: intent, impact walk and effort of a change

The people stay where the decisions are: the business answers questions and accepts at G2, G3 and G7, engineers decide G4 to G6, operations G8.

Planned

  • A status board per specification: every document with its open questions, rounds and gate results.
  • A quality dashboard and trend reports from the evidence kept at the gates.
  • TomSpecs tools for Phases 5 to 8, starting with the impact walk and expected-to-fail tests for changes.

The full process definition, with every gate's criteria, the issue workflow and the upgrade cycle, is the TomSpecs project flow.